Subdivision switchboards and metering requirements

EGT Apprentice News Banners (9)

Site Main Switchboard (SMSB) requirements

Approval and requirements:

  • The requirement for an SMSB is part of the West Australian Planning Commission (WAPC) approval process.
  • Compliance with Western Power and Horizon Power standards is essential for power supplies to a lot.

Installation and clearance:

  • Electrical contractors must supply and install a SMSB as part of the approval process.
  • A clearance certificate will not be issued to the land developer until a Notice of Completion is received.

Guidelines and references:

Considerations:

  • Verify the location, size, and type of SMSB required based on the type of subdivision (e.g., freehold or strata).
  • Take into account the number of units on site, as this will affect the size of consumer mains and SMSB.

Metering and equipment

Installation standards:

  • Adhere to WAER and WASIR metering regulations for all metering and associated equipment.

Considerations:

  • Ensure that Distributed Master Metering and Multiple Master Metering are not mixed on the same site.
  • We encourage electrical contractors to thoroughly review these requirements and guidelines to ensure full compliance and to avoid potential issues.

For further assistance or detailed guidance, please contact ECA Technical on (08) 6241 6100 or technical@ecawa.org.au.

 